MUNICIPAL ENGINEERING PROJECTS

SANITARY PUMP STATION & FORCE MAIN REPLACEMENT

East Bloomfield, NY

Back to Gallery


Problem

The Town of East Bloomfield's 40 year old sanitary pump station and 2,000 linear foot force main had experienced numerous equipment failures since replacement pumps were installed in 1995.

CLIENT
Town of East Bloomfield
East Bloomfield, NY

SERVICES PROVIDED
- Design
- Construction Documents
- Cost Estimating
- Construction Administration

Solution

Thornton Engineering was retained to evaluate service area needs and to design a more efficient pump station system.

Thornton Engineering provided design, pump specifications, and construction documents for the replacement of the duplex submersible pump station and force main.

Construction sequencing plans provided specific instructions and details to accomplish the work while maintaining service for the Crosman factory and residential connections.